«StroiReanimatsiya» corporate group acted as general designer and general contractor for construction works on two government contracts.
Major overhaul of rooms to place rehabilitation center.
- Performed major overhaul in rooms of completely unpowered building of the former training center with redevelopment of rooms and installation from scratch of all partitions.
- As part of the project, were made general construction and engineering works in rooms with total area of over 900 sq.m.
- Performed transfer of main switchboard from the existing second floor to the technical floor of the building.
- Replacement of all engineering works and communications.
- Assembled a large passenger elevator for two stops.
- Installed special ramps for movement of patients with limited mobility.
Major overhaul of reanimation and shock therapy departments.
- Was made installation of air-conditioning medical modules of clean rooms in reanimation wards and in the hallway of operation unit.
- Complete replacement of all engineering systems, including installation of new ventilation system with 3-stage filtration system.
- Installation of central medical gas supply system which is composed of 4 gases, including equipping of reanimation wards with life support systems (reanimation consoles) in the amount of 24 pieces manufactured by CJSC "Alternative science".
- Performed general construction and engineering works in rooms with total area of about 800 sq.m.