Major overhaul in rooms for placement the angiography machine.
Within the project was made major overhaul of rooms with partial redevelopment, performed the constructive strengthenings of overlappings of the building due to the significant weight loads of technological equipment.
- Performed installation of air-conditioning medical modules of clean rooms in: operating room, control room, pre-operative room.
- Were held actions to provide protection from X-ray radiation.
- The total area of “clean areas” reached 58.6 sq.m.
- Installation of ventilation system on the basis of ventilation unit manufactured by company «A-Clima» with three-stage filtration and organization of vent chamber on the technical floor.
- Equipment installation for medical gas supply, manufactured by CJSC "Alternative science".
- Within the major overhaul was made the replacement of all engineering networks.
- Performed general construction and engineering works in all rooms with total area of about 180 sq.m.